Applied Digital (NASDAQ: APLD) has reached Ready for Service on schedule for the first 25 MW data hall at its Polaris Forge 2 campus in Harwood, North Dakota. It also completed base-build commissioning for the first 75 MW of the campus's initial 150 MW building.
The building is fully leased to a hyperscaler as part of the customer's 200 MW long-term lease at Polaris Forge 2.
Three Halls at a Time
Each 150 MW building at the campus is commissioned in two 75 MW phases. In each phase, three 25 MW data halls are tested and commissioned together. Here's where the first phase stands:
25 MW: integrated fit-out complete and Ready for Service
50 MW: base-build tested and commissioned, so it can now advance through fit-out and customer delivery
Campus Number Two
This is the first Ready for Service milestone at Applied Digital's second AI Factory campus. It follows the delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.
Chairman and CEO Wes Cummins tied the milestone to repeatability. "With our second campus now reaching Ready for Service on schedule, we're demonstrating that our execution model is repeatable," he said.
Backed by Leases
The Harwood building is part of Applied Digital's portfolio of more than $41 billion in contracted base-term lease revenue. Cummins said AI infrastructure demand "is not theoretical for us" and is "backed by long-term customer commitments."
One hall in Harwood is ready for service. The other two in this phase now move on to fit-out.