Source: Marriott
DPR Construction has completed Hotel Trinity, a 14-story, 258-room Autograph Collection hotel at 311 E. 5th St. in downtown Austin. The White Lodging development is now open, DPR announced Nov. 17.
The build took 24 months, from October 2024 to September 2026, on a tightly constrained corner site at 5th and Trinity. The tally:
About 177,000 square feet
About 6,700 square feet of meeting space
About 1,200 skilled craft workers, with roughly 325 at peak
More than 175,000 worker hours
More than 50 trade partners
The hotel also features the Yacht Club, a ground-floor seafood restaurant, and Sundeck Social, an exclusive rooftop pool and social club.
Good Fences, Good Neighbors
Before demolition, the DPR team led a year-long effort to relocate, disconnect and refeed active utilities serving neighboring properties. That included telecom and internet service, and a new water feed for the historic Antone’s Nightclub next door.
Then came the fast part. Two existing structures came down on a compressed two-week schedule, with JR Ramon Demolition as the demolition partner.
The wall shared with Antone’s got its own carefully sequenced plan for separating the buildings without disrupting the venue. Call it demolition with a scalpel.
The team also used dust and erosion control, street cleaning, and noise and vibration monitoring.
The Night Shift Skin
The prefab exterior wall panels were built off-site and installed overnight. That sped up enclosure, reduced impacts on downtown traffic and hit an expedited dry-in that kept weather delays to a minimum.
“Building in a dense downtown environment requires looking beyond the boundaries of the jobsite,” said Bryan Kent, DPR’s Central Texas business unit leader.
On a downtown job like this one, the scope of work doesn’t stop at the property line.