Dallas Fort Worth International Airport has lifted all six prefabricated modules into place for their new Terminal F Skylink Station. The station will connect Skylink to the future Terminal F, and DFW announced the milestone on November 3, 2026.
Heavy Metal Night Shift
The station was built using modular construction. The modules were assembled at ground level, then transported and lifted onto the active Skylink guideway.
That job called for a heavy-lift crawler crane, which needed plenty of assembly itself. It arrived in roughly 60 truckloads and took nearly two weeks to put together before lifting could begin.
Each module weighed between 210 and 310 tons. The heaviest one weighs about as much as a fully loaded Boeing 777, a fitting comparison for an airport project.
Every lift took place overnight and ran about eight hours. Each one needed precise alignment to tie the new station into the existing Skylink system.
By working this way, DFW kept the impact on airport operations to a minimum. They also avoided the extended Skylink shutdowns that traditional methods would have required.
Construction now moves to structurally connecting the modules and integrating them into the finished station.
Gate Expectations
Terminal F will be DFW’s sixth terminal, with an estimated cost of $4 billion.
The first phase of the Terminal F expansion program is anticipated to open 15 gates in 2027. The terminal is planned to ultimately deliver 31 gates, all served by American Airlines.
Terminal F is also planned to expand capacity for international and widebody operations. Plans include areas for parking, ticketing, check-in, security screening, and baggage operations. The final configuration will also provide a walking connection with Terminal D.
Snapshot:
Project: Terminal F Skylink Station
Airport: Dallas Fort Worth International Airport
Location: DFW Airport, Texas
Construction Method: Modular, with six prefabricated structural modules
Module Weights: 210 to 310 tons each
Equipment: Heavy-lift crawler crane, delivered in about 60 truckloads and assembled over nearly two weeks
Lift Duration: About eight hours per lift, done overnight
Status: All six modules set
Next Step: Structural connection and integration of modules
Terminal F: DFW’s sixth terminal
Terminal F Value: Estimated $4 billion
Terminal F Phase 1: 15 gates, anticipated 2027
Terminal F Planned Total: 31 gates, served entirely by American Airlines
Terminal F Scope: International and widebody capacity; parking, ticketing, check-in, security screening, and baggage operations
Additional Connection: Walking connection with Terminal D in final configuration
More Info: dfwairport.com/construction
TheJobWalk Thoughts
DFW chose to set modules onto an active guideway overnight instead of shutting Skylink down for an extended stretch. That says a lot about their priorities: keep the airport moving. Airports with live operations tend to reward teams that can build offsite, work tight overnight windows, and tie into existing systems cleanly.
Phase one is anticipated to open 15 gates in 2027, and the terminal is planned to ultimately deliver 31. DFW hasn’t said how or when the rest will arrive. Suppliers interested in this program should keep watching it past 2027 rather than treating phase one as the whole story.