The Daily Dig:

Lamar County School District has broken ground on replacement campuses for Purvis High School and Sumrall High School. Combined construction cost is $86 million, funded through a $117 million voter approved bond passed in November 2024.

The Purvis campus is going up directly across from the existing school. Sumrall's new campus sits along MS-44, near its current site. MP Design Group is leading design on both. The district expects students to be on both new campuses by Fall 2027.

Project Snapshot:

  • Owner / Developer: Lamar County School District

  • Design Team: MP Design Group

  • Sector: K-12 Education

  • Budget (Two Projects Combined): $86M (Bond-Funded)

  • Funding Mechanism: $117M voter-approved bond (Nov. 2024)

  • Location: Lamar County, Mississippi (Purvis & Sumrall)

  • Status: Groundbreaking complete; publicly bid under stipulated sum contract

  • Target Occupancy: Fall 2027

TheJobWalk Thoughts:

Contracts are signed and ground is broken, pre-construction is done. Regional subs and suppliers should be tracking prime awards and getting in front of GC procurement teams now. Bond funded school work is clean: money is locked, oversight is real, and Fall 2027 isn't moving. Lock in your manpower and material commitments before the rest of the market catches up.