Source: Lithium Americas
Lithium Americas released an update on its Thacker Pass lithium project in Nevada on November 11, 2026, raising the Phase 1 capital cost estimate to $3.83 billion, up from $2.93 billion. Mechanical completion is still targeted for late 2027.
Production is expected to ramp up through 2028, with Phase 1 designed for a nominal 40,000 tonnes per year of battery-quality lithium carbonate.
Follow the Overrun:
Labor install rates for piping, steel and equipment: about $245 million
Craft labor wages and compensation: about $150 million
EPCM and contractor staff wages: about $150 million
Additional contingency: about $150 million
Tariffs and logistics: about $100 million
EPCM and contractor staffing levels: about $100 million
Together, the two craft labor lines and the two EPCM lines come to $645 million, more than 70% of the $895 million in incremental capital expenditure. The company says regional competition is stretching union labor availability beyond what it expected.
On the EPCM side, the company says Bechtel, the project’s EPCM contractor, and its contractors required more engineers and construction staff to complete the project.
Tariffs came in below the earlier estimate. Now that most equipment and materials have arrived, tariff exposure is estimated at about $60 million, down from the previously disclosed range of $80 million to $100 million.
Headcount Climbing
As of September 30, 2026, about 1,900 personnel were on site, including over 1,600 craft workers, with roughly 2,200 expected by year end. Crews had logged 4.7 million work hours without a serious injury or lost-time incident.
Covering the Gap
The company now expects to spend $1.7 billion to $2.0 billion on Thacker Pass Phase 1 in 2026, up from earlier guidance of $1.3 billion to $1.6 billion. It puts its incremental funding requirement at about $995 million.
To cover it, the company expects to contribute $650 million to its joint venture with GM and to use $315 million in DOE Loan reserve account funds. Loan amendments will also trim a reserve requirement by about $30 million.
Those contributions will raise Lithium Americas’ stake in the JV. The final ownership split is still being worked out with the DOE and GM.
As of September 30, 2026, the company had about $1.3 billion in total cash and restricted cash, including $359.5 million at the JV.
What’s Left to Beat
Detailed engineering is complete, and the earthworks and geotechnical risks have passed. The company says its primary remaining risks are the costs of attracting and keeping quality craft labor and sustaining planned install rates.
Thacker Pass has the lithium. Its main remaining risks now center on the workforce.