The Daily Dig

American Electric Power plans to invest about $4 billion in a 702-megawatt fuel cell power plant near Cheyenne, Wyoming. Google will buy the power under a 20-year power purchase agreement.

That power will come from Cheyenne Fuel Cell, LLC. AEP owns and controls approximately 92% of the company, and funds advised by Basalt Infrastructure Partners hold nearly 8%.

AEP is leading development and construction. Work is set to start in 2026, with the plant expected to be fully running by the end of 2028.

Gas, No Flame

The plant will run on fuel cell technology from Bloom Energy. It produces electricity without burning natural gas, and it’s built to deploy quickly for customers with heavy power demands.

AEP also plans to add carbon capture, aiming for near-zero emissions.

“As power demand continues to grow, AEP is bringing together new technologies and strong partnerships to deliver reliable, innovative energy solutions quickly and at scale,” said Bill Fehrman, AEP chairman, president and chief executive officer.

❝

Snapshot:

Power Supplier Entity: Cheyenne Fuel Cell, LLC

Development and Construction Lead: American Electric Power

Ownership: AEP (approx. 92%); funds advised by Basalt Infrastructure Partners, LLP (nearly 8%)

Offtaker: Google

Agreement: 20-year power purchase agreement

Technology Provider: Bloom Energy

Location: Near Cheyenne, Wyoming

Sector: Power generation

Capacity: 702 megawatts

Investment: Approximately $4 billion

Emissions Plan: Non-combustion fuel cells with planned carbon capture

Construction Start: 2026

Full Operation: End of 2028

Developer HQ: Columbus, Ohio

TheJobWalk Thoughts

Wyoming isn’t on AEP’s home map, and Fehrman’s quote points to customers beyond their traditional territory. A utility building dedicated generation for a single tech customer, under a 20-year contract, gives the project long-term revenue visibility. That’s the kind of owner subs want on their bid list.

Fuel cells are modular, so expect repeatable work on pads, gas piping, and electrical balance of plant rather than one massive structure. The carbon capture plan is still light on public detail, with no provider or contractor named yet. Sales teams, that door’s worth a knock.