Both tracks on the new Portal North Bridge are now in full service, NJ TRANSIT and Amtrak announced November 16. Governor Mikie Sherrill joined agency officials in Kearny, NJ, to mark the retirement of the Portal swing bridge, in service over the Hackensack River since 1910.
The old bridge had to swing open for marine traffic. Its replacement is a fixed span that rises 50 feet over the river, doubling the height clearance. Boats can now pass underneath without interrupting trains.
One Track at a Time
Service moved to the new bridge in two stages, and the old bridge stayed in operation during the first:
Track one: February 13 to March 15
Track two: October 9 to November 16
Regular weekday service resumed November 16, and weekday Midtown Direct diversions to Hoboken have ended.
Heavy on the Foundations
In October 2021, Skanska/Traylor Bros PNB Joint Venture was awarded the $1,559,993,000 construction contract. It’s the single largest construction award in NJ TRANSIT history. The project spans 2.44 miles of the Northeast Corridor, and its estimated materials include:
45 million pounds (23,000 tons) of steel
219,000 cubic yards of concrete
185,000 linear feet (35+ miles) of pipe piles
20,000 linear feet (3+ miles) of drilled shafts
That’s more than 38 miles of piles and shafts on a project spanning 2.44 miles.
The project was funded by the U.S. Department of Transportation, New Jersey, New York and Amtrak. FTA Region 2 Administrator Michael Culotta cited a $926 million FTA investment.
Gateway’s First Finish
Senator Cory Booker called Portal North the first of the Gateway Program’s 11 projects to be completed. Gateway will eventually double rail capacity between Newark and New York.
The old swing bridge is scheduled to be dismantled in 2027. After 116 years of opening for boats, it’s closing for good.