RWE and Google have signed a 15-year power purchase agreement covering the full output of the 155MWac Crooked Creek Solar project in McCurtain County, Oklahoma. It marks RWE's first solar project in the state.

Construction is scheduled to begin later this year, with commercial operation expected in 2028. The electricity will support Google's operations in the Southwest Power Pool market.

RWE says the project will also deliver long-term economic benefits to McCurtain County and surrounding communities. Construction alone is expected to create up to 250 jobs at peak activity, generating an estimated $24.3 million in local economic activity and $1.4 million in state and local tax revenue.

Once operational, RWE projects the facility will contribute roughly $25 million toward county programs, local emergency medical services, the Broken Bow School District, and regional technology education centers.

The agreement builds on RWE's existing presence in Oklahoma. The company owns and operates the 148MW Boiling Springs wind project in Woodward County and has six more power projects, totaling 1.6GW, in development across the state.

Snapshot:

Project Name: Crooked Creek Solar

Developer: RWE (RWE Americas)

Offtaker: Google

Agreement Type: 15-year power purchase agreement (full output)

Capacity: 155MWac

Location: McCurtain County, Oklahoma

Market: Southwest Power Pool

Construction Start: Later in 2026

Commercial Operation: 2028

Peak Construction Jobs: Up to 250

Construction Economic Impact: $24.3 million (local)

Construction Tax Revenue: $1.4 million (state and local)

Projected Local Revenue and Benefits: Approximately $25 million, for county programs, EMS, Broken Bow School District, and regional technology education centers

RWE Other Oklahoma Assets: Boiling Springs wind project (148MW, Woodward County)

RWE Oklahoma Pipeline: Six additional projects, 1.6GW total, in development

TheJobWalk Thoughts

Google's role as offtaker signals real demand for solar capacity in the Southwest Power Pool. When hyperscalers commit to full-output PPAs, it's a strong read on where power buyers see reliable, affordable generation coming from next.

The 250 peak construction jobs and 2026 to 2028 timeline give local labor and subcontractors a defined window to plan around, with clear dollar figures attached for county impact.

RWE's six-project, 1.6GW Oklahoma pipeline is the bigger story here. Crooked Creek is one piece of a much larger buildout, and contractors chasing Oklahoma renewable work should track how quickly the rest of that pipeline moves.