The Gateway Development Commission (GDC) announced on November 18 that the Hudson Tunnel Project’s second tunnel boring machine is mining the new rail tunnel’s southern tube. The northern machine launched in October, so both tubes are now under construction.

Rock Now, River Later

Both machines are cutting the first 5,100 feet in New Jersey, from the tunnel portal in North Bergen to the Hudson County Access Shaft on the Weehawken and Hoboken border.

As of the announcement, the northern machine had bored about 400 feet and installed more than 60 lining rings. That’s under a tenth of the way to the shaft.

At the shaft, both machines will be pulled and replaced by a second pair built for the mixed ground under the Hudson River. Including scheduled maintenance pauses, this stretch will take about a year.

Source: The Gateway Development Commission (GDC)

Built for the Palisades

  • Single shield machines designed for hard, dry rock

  • Cutterheads measuring 28 feet, 8 inches in diameter

  • Trailing gantries that extend roughly 500 feet and weigh more than 1,680 tons

  • Nearly 850 lining rings per machine, assembled from more than 5,000 segments

Dig and Line in One Pass

These machines excavate and line the tunnel at the same time. Disc cutters break the rock into chips, and a conveyor carries them out the back.

As the machine advances, an erector arm places precast concrete segments to form the permanent lining. Hydraulic thrust jacks brace against that lining to push forward.

Source: The Gateway Development Commission (GDC)

Who’s Running the Show

This first stretch, along with the access shaft, falls under the Palisades Tunnel Project, one of ten construction packages. Schiavone Lane Dragados JV leads construction, and the Port Authority of New York and New Jersey manages delivery with GDC.

Next stop: the access shaft, where a second pair takes over for the river.