Site preparation has begun at the proposed site of Tesla’s $10.1 billion solar manufacturing project in Fort Bend County, Texas. That’s according to a drone video dated November 8 from videographer S. E. Robinson, Jr., as reported by Tesla North.
The footage follows Fort Bend County’s approval of four incentive agreements for Project Crystal Sun in October.
Lay of the Land
The proposed site covers roughly 3,000 acres near FM 762 and FM 1994, south of the Brazos River and near Needville.
On November 9, Elon Musk posted “Project Crystal Sun” on X while sharing Sawyer Merritt’s post saying construction had officially begun. Musk’s own comment offered no construction schedule, production target, or other details.
Equipment Heavy
Lamar CISD’s summary of Tesla’s application says the proposed facility would manufacture photovoltaic solar cells and/or assembled solar modules. The plan includes:
About $8.6 billion for equipment and other personal property
$1.5 billion for real property
Commercial operations anticipated in the first quarter of 2029
About 9,712 permanent jobs by 2033
That means roughly 85% of the proposed investment would go toward equipment and other personal property.
Not Set in Concrete
Site preparation alone doesn’t establish the status of the full factory project. The timeline and jobs figures are forecasts, and the video doesn’t confirm them.
The district’s summary also says Tesla was evaluating alternative locations and hadn’t made a final site selection decision. The social posts don’t say whether every incentive agreement and approval is complete.
Tesla’s solar expansion in Buffalo, announced earlier this year, includes an initial annual module capacity of 300 megawatts. Crystal Sun would add a much larger manufacturing project to Tesla’s solar business.
For now, the footage shows real work on the ground, while the bigger questions stay up in the air.