SPP's Board of Directors has cleared $23.7 billion in transmission projects to move toward construction. At its Nov. 17 meeting, the board approved the 2026 Integrated Transmission Plan and authorized notification to construct (NTC) letters for select projects.
The portfolio includes new and upgraded transmission lines. SPP evaluated more than 14,000 potential projects and worked with hundreds of stakeholders over two years to put it together.
Nine Lines, Not 41
The plan includes a 765 kV backbone that SPP calls an "expressway" for ultrahigh voltage transmission. In the buildout SPP evaluated:
The 765 kV option requires nine lines
A 345 kV alternative requires 41 lines and costs approximately 1.9 times as much
Per SPP, 765 kV lines can serve rapid load growth over longer distances with lower losses.
The Load Behind the Lines
The study projects that peak demand could climb from about 58 GW in 2026 to about 72 GW by 2030. By 2035, it could hit 96 to 110 GW.
The wires are already feeling it. Distinct peak transmission constraints rose from 115 in 2016 to 302 in 2025.
What the Lines Buy:
About 35 GW of additional transfer capability
The potential to add about 40 GW of capacity to connect new electricity customers and generation
$76 billion to $215 billion in modeled adjusted production cost benefits over 40 years, in net present value
SPP notes that customer impacts will vary based on cost allocation and other factors.
The board has signed off. Now the plan moves from the drawing board to the field.