1: Meta Hyperion · Richland Parish, LA

Meta is developing its $50 billion-plus Hyperion data center campus in Richland Parish, Louisiana. The expanded development will span nearly 10 million square feet and support up to 5 GW of IT capacity.
Construction began in December 2024, with Turner Construction, DPR Construction and Mortenson delivering the initial development. Turner's Phase 1 scope includes four AI data center buildings, while DPR is delivering approximately 2 million square feet of data space and supporting infrastructure.
Phase 2 will add 10 buildings totaling approximately 5.5 million square feet. Turner and Mortenson are delivering the expansion, with preconstruction and procurement underway. Construction is scheduled to begin in June 2027.
Meta has committed to investing more than $1 billion in local infrastructure, including roads, water and wastewater systems. Its agreement with Entergy supports seven additional proposed natural gas plants, three battery storage facilities and major grid improvements.
The campus was originally planned to come online in phases through 2030, although an updated completion schedule remains unconfirmed. Hyperion is expected to support more than 7,500 peak construction workers.
Owner: Meta / Blue Owl-managed funds JV (20% / 80%)
Developer: Meta Platforms
Construction Team: Turner Construction, DPR Construction, Mortenson (general contractors); U.S. Engineering (mechanical), Faith Technologies (electrical), Digital Building Components (prefabricated exterior panels). Turner and Mortenson selected for Phase 2.
Investment Value: $50B+ announced investment
Scope: Original 2,250-acre site plus approximately 1,400 additional acres reportedly acquired; nearly 10M SF, up to 5 GW IT capacity; Phase 2 includes 10 buildings totaling 5.5M SF
Timeline: Construction began December 2024; Phase 2 scheduled to begin June 2027; final completion unconfirmed
Location: Former Franklin Farm megasite, along Louisiana Highway 183, near Holly Ridge, Richland Parish, Louisiana.
2: Oracle / OpenAI Project Jupiter · Doña Ana County, NM

STACK Infrastructure and BorderPlex Digital Assets are developing Project Jupiter, a four-building AI data center campus near Santa Teresa, New Mexico, that will supply Oracle computing capacity for OpenAI. It carries a minimum $50 billion five-year capital commitment, including infrastructure and equipment.
Clayco and Kiewit New Mexico Co. began construction in 2025. The first 855,000 square foot section has topped out, with work over 30% complete as of October 2026. By October 13, 4,393 workers had logged over 3.75 million labor hours, with a projected 7,000-worker peak.
The approximately 1,400-acre development includes data centers, power infrastructure and expansion land. A proposed Bloom Energy fuel-cell microgrid would provide up to 2.45 GW of generation capacity, supported by the planned 17.8-mile Green Chile natural gas pipeline.
Power permitting remains a key hurdle. Oracle announced design revisions on October 15 to reduce permitted emissions by 35%. A proposed El Paso Electric agreement for construction, commissioning and backup power also faces county objections.
The initial 400-acre development targets completion in Q3 2028, although permitting challenges and a September force majeure notice linked to power concerns create schedule uncertainty.
Owner: Project entities associated with STACK Infrastructure and BorderPlex Digital Assets; Yucca Growth Infrastructure (separate microgrid entity)
Developer: STACK Infrastructure; BorderPlex Digital Assets (original development partner)
Construction Team: Clayco, Kiewit New Mexico Co. (construction partners); APIC Solutions (electrical and low-voltage cabling); Bloom Energy (fuel-cell supplier)
Investment Value: Minimum $50B five-year capital commitment, including equipment
Scope: Four data center buildings, approximately 1,400 acres, up to 2.45 GW planned fuel-cell capacity
Timeline: Construction began 2025; initial 400-acre development targeted Q3 2028; microgrid permitting pending
Location: Santa Teresa Industrial Park, near Santa Teresa, Doña Ana County, New Mexico
3: Vantage Frontier · Shackelford County, TX

Vantage Data Centers is developing Frontier, a $25 billion-plus AI data center campus in Shackelford County, Texas, as part of Oracle and OpenAI's Stargate expansion.
The campus will feature 10 single-story data centers totaling 3.7 million square feet, with up to 1.4 GW of critical IT capacity. The buildings will support high-density AI racks with liquid cooling and closed-loop chiller systems.
Kiewit is the general contractor, with construction underway since 2025 and a formal groundbreaking held in December. VoltaGrid is providing behind-the-meter power infrastructure, with an initial natural gas generation installation of approximately 700 MW planned.
By June 2026, Oracle reported 115 MW of power capacity already online, more than a month ahead of schedule.
Vantage originally targeted its first building for delivery in H2 2026, while Oracle now expects initial customer delivery in H1 2027. State filings schedule additional buildings through 2028, with final campus completion unconfirmed.
Owner: Vantage Data Centers, through project-specific subsidiaries
Developer: Vantage Data Centers
Construction Team: Kiewit (general contractor); RK Mechanical (mechanical contractor); VoltaGrid (onsite power infrastructure); CSI Engineering (MEP verification and commissioning); Thompson Engineering (lead engineering partner, per CSI)
Investment Value: $25B+ announced total campus investment
Scope: 1,200 acres, 10 buildings, 3.7M SF, up to 1.4 GW critical IT capacity; approximately 700 MW planned initial onsite generation
Timeline: Construction underway in 2025; groundbreaking December 2025; first building originally targeted H2 2026; initial customer delivery expected H1 2027; additional buildings scheduled through 2028
Location: 246 PR 1604, Abilene, TX 79601, Shackelford County, Texas
4: Meta El Paso · El Paso, TX

Meta is developing an approximately $14 billion AI data center campus on roughly 1,000 acres in northeast El Paso, Texas. Expanded in March 2026, the development will deliver up to 1 GW of planned computing capacity.
Construction began in October 2025, with JE Dunn and Hensel Phelps serving as general contractors. The original project covered approximately 1.2 million square feet, with development potentially spanning five phases.
An April 2026 filing under Project Seafox identifies 12 new buildings, five substations and site work across approximately 600 acres, with projected completion in February 2029. Total expanded building area remains unconfirmed.
In July 2026, Meta announced a joint venture with BlackRock-managed funds to finance approximately $14 billion in development costs, covering buildings, power, cooling and connectivity infrastructure.
The campus will use closed-loop liquid cooling. Per Meta, the project backs $500 million in new El Paso Electric generation and $410 million in grid upgrades. The proposed 366 MW McCloud gas plant won conditional recommendation for regulatory approval in September 2026.
More than 2,300 workers were onsite in July 2026, with over 4,000 expected at peak construction. Initial operations are targeted for 2028.
Owner: BlackRock-managed funds (80%) / Meta (20%) joint venture
Developer: Meta Platforms; Wurldwide LLC (local project entity)
Construction Team: JE Dunn Construction, Hensel Phelps (general contractors); Stantec (engineer of record for Project Seafox)
Investment Value: Approximately $14B in announced total JV development costs, including buildings and long-lived infrastructure
Scope: Approximately 1,000 acres, up to 1 GW capacity, up to five potential phases; Project Seafox filing covers 12 new buildings, five substations and approximately 600 acres of site work
Timeline: Construction began October 2025; initial operations targeted 2028; Project Seafox filing lists February 2029 completion; final campus completion unconfirmed
Location: 7001 Stan Roberts Sr. Avenue (Project Seafox filing address), northeast El Paso, TX 79934, near U.S. Highway 54
5: Meta Lebanon · Lebanon, IN

Meta broke ground on its $10 billion-plus AI data center campus in Lebanon, Indiana, on February 11, 2026. Located within the LEAP Innovation and Research District, the development will deliver up to 1 GW of planned capacity.
The 1,500-acre campus will feature 13 buildings totaling approximately 4 million square feet, including 10 data centers and three support facilities. Construction could span as many as six phases.
Turner Construction and Mortenson are building alongside Faith Technologies, which is adding near-site manufacturing and integration facilities and two warehouse hubs. Meta pledged over $120 million for water, roads, transmission lines and utilities.
The facilities will use closed-loop liquid cooling and target LEED Gold certification. Meta is coordinating power infrastructure with Boone Power and Wabash Valley Power Alliance.
Initial operations are targeted for late 2027 or early 2028, with no confirmed revised schedule. The project is expected to support more than 4,000 construction jobs at peak and approximately 300 permanent positions.
Owner: Meta Platforms
Developer: Meta Platforms
Construction Team: Turner Construction, Mortenson (construction contractors); Faith Technologies (construction, manufacturing and integration partner)
Investment Value: $10B+ announced investment to construct and outfit the campus, including related community infrastructure
Scope: 1,500 acres, approximately 4M SF, 13 buildings including 10 data centers, up to 1 GW planned capacity
Timeline: Groundbreaking February 11, 2026; up to six potential phases; initial operations targeted late 2027 or early 2028; final completion unconfirmed
Location: LEAP Innovation and Research District, along State Road 32 east of County Road 450 West, Lebanon, Boone County, Indiana